ID DATE PROCESS COMMENTS PICTURES
1718April 27, 2017ShippedOn its way
1717April 27, 2017InstallFully tested and on the crate.
1712April 27, 2017InstallInstallation complete
1711April 26, 2017Ordering
1707April 26, 2017BrainComplete
1697April 20, 2017InstallHybrid system installed
1693April 20, 2017Installmotors installed.
1684April 17, 2017InstallAlmost there
1681April 13, 2017Powder CoatCompleted
1680April 12, 2017WeldingWelding Complete, sending to powder coat dept.
1659April 04, 2017MachiningComplete
1658April 07, 2017FormingForming complete. Ready for welding.
1655March 31, 2017MachiningStarted
1650March 30, 2017CleaningChipping, Grinding & Oscillating Complete
1648March 30, 2017PlasmaComplete
1644March 29, 2017BandSawComplete