ID |
DATE |
PROCESS |
COMMENTS |
PICTURES |
2106 | August 18, 2017 | Shipped | On its way |  |
2101 | August 18, 2017 | Tested | Passed Testing! |  |
2096 | August 16, 2017 | Brain | Complete |  |
2062 | August 07, 2017 | Install | Installation complete |  |
2060 | August 04, 2017 | Cleaning | grinding/oscillating complete |  |
2058 | August 04, 2017 | Wires | completer |  |
2047 | August 02, 2017 | Install | Elevation system installed |  |
2045 | August 02, 2017 | Powder Coat | Powder coating done. Ready for assembly. |  |
2017 | July 29, 2017 | Welding | Welding Complete, ready to powder coat |  |
1998 | July 24, 2017 | Machining | Complete |  |
1975 | July 19, 2017 | Forming | Forming complete. Ready for welding. |  |
1970 | July 17, 2017 | BandSaw | Complete |  |
1943 | July 10, 2017 | Cleaning | Grinding/oscillating complete |  |
1938 | July 05, 2017 | BandSaw | Almost Complete |  |
1932 | July 03, 2017 | Cleaning | Chipping complete |  |
1926 | June 30, 2017 | BandSaw | Started |  |
1923 | June 30, 2017 | Plasma | done |  |
1918 | June 28, 2017 | Plasma | Halfway Done |  |
1917 | June 28, 2017 | Cleaning | Chipping almost complete |  |